Case Studies / Downstream

🇸🇦 Jubail Refinery Turnaround Wastewater

Jubail Industrial City, Saudi Arabia

Project Overview

A 400,000 BPD Saudi refinery required a 6-week turnaround across 8 process units. Wastewater flows were expected to peak at ~12,000 m³/day — roughly 8× normal — and contained hydrocarbons, caustic, spent cleaning chemicals, and heat-exchanger fouling products that exceeded the existing ETP capacity.

The Challenge

The refinery's installed effluent treatment plant could not handle the turnaround surge. Any water-side bottleneck would directly delay return-to-service for the cracker and hydrotreater units, with significant lost-margin exposure per day of delay.

WFS Solution

WFS deployed a temporary 12,000 m³/day rental train: equalization tankage, primary oil-water separation, two large-skid DAF units, multimedia filtration, and biological polishing tied into the refinery's existing outfall. A resident WFS operations crew ran the train 24/7 for the turnaround duration.

Technologies Applied

  • Equalization & Surge Storage
  • API Oil-Water Separation
  • Large-Skid DAF (XL Train)
  • Multimedia Filtration
  • Biological Polishing

Results Achieved

11,800 m³/day
Peak Flow Handled
100%
Regulatory Compliance
Zero days
Turnaround Delay (water)
Repeat
Contract Awarded

Performance Outcomes

  • Peak flow of 11,800 m³/day treated to refinery's discharge spec
  • Zero regulatory exceedances over the 6-week turnaround
  • No turnaround delay attributable to water handling
  • Operator awarded WFS the next two turnarounds under the same framework

Your Project Could Be Next

Talk to a WFS engineer about your specific water challenge.